1.0
Objective
UCLA's DBF team finished 3rd in the world in 2026. I designed, built and assembled the landing gear for P2, laid up carbon-fibre fuselage skins, built airframe structure, supported the 252-inch tow-banner deployment mechanism, and helped rebuild P2 in seven days after it was lost in a test flight.
2.0
Hardware

3.0
Work performed
- 3.1Designed, manufactured and assembled the P2 landing gear: a trailing-link main gear whose lower strut pivots against an extension spring, and a bent steel-wire nose gear. It held through every high-velocity landing at competition.
- 3.2Performed carbon-fibre hand layups for the fuselage to improve airframe durability.
- 3.3Manufactured aircraft structures and supported the deployment mechanism for a 252-inch tow banner.
- 3.4Rebuilt and upgraded P2 within seven days after a test-flight failure, coordinating manufacturing, assembly and design changes to make the competition deadline.
4.0
Specification
| Aircraft | P2 · banner-towing mission |
|---|---|
| My parts | Main and nose landing gear · fuselage layup · banner deployment support |
| Main gear | Laser-cut trussed plate struts · pinned lower link · music-wire extension spring · set-screw collar axle |
| Nose gear | Bent steel wire strut in a printed block |
| Methods | SolidWorks · laser cutting · carbon-fibre hand layup |
| Result | 3rd place worldwide |
5.0
Plates
6.0
Anomaly report
Closed
- Observed
- P2 was lost in a test-flight failure shortly before competition.
- Corrective action
- Rebuilt and upgraded the aircraft in seven days, folding design changes into the rebuild. The new landing gear survived every competition landing.
- Lesson
- A schedule with no margin still has to fly. Parallel manufacturing and assembly made the week possible.